信息系统项目管理师历年真题英语题翻译与答案[9]

2016年04月22日来源:信管网 作者:cnitpm



2007年下半年
● Project Quality Management processes include all the activities of the (71) that determine quality policies, objectives and responsibilities so that the project will satisfy the needs for which it was undertaken.
(71)A. project B. project management team
C. performing organization D. customer
Cnitpm参考答案:C

● The project team members should also be aware of one of the fundamental tenets of modern quality management: quality is planned ,designed and built in, not (72 ).
(72)A. executed in B. inspected in
C. check-in D. look-in
Cnitpm参考答案:B

● The project (73)is a key input to quality planning since it documents major project deliverables, the project objectives that serve to define important stakeholder requirements, thresholds, and acceptance criteria.
(73)A. work performance information B. scope statement
C. change requests D. process analysis
Cnitpm参考答案:B

● Performing (74)involves monitoring specific project results to determine if they comply with relevant quality standards and identifying ways to eliminate causes of unsatisfactory results.
(74)A. quality planning B. quality assurance
C. quality performance D. quality control
Cnitpm参考答案:D

●(75) involves using mathematical techniques to forecast future outcomes based on historical results.
(75)A. Trend analysis B. Quality audit
C. Defect repair review D. Flowcharting
Cnitpm参考答案:A

2006年下半年
● (66) from one phase are usually reviewed for completeness and accuracy and approved before work starts on the next phase.
(66)A.Process B.Milestone C.Work D.Deliverables cnitpm参考答案:D
Cnitpm解析:

● Organizations perform work to achieve a set of objectives. Generally, work can be categorized as either projects or operations, although the two sometimes are (67) .
(67)A.confused B.same C.overlap D.dissever cnitpm参考答案:C
Cnitpm解析:



● In the project management context, (68) includes characteristics of unification, consolidation, articulation, and integrative actions that are crucial to project completion, successfully meeting customer and other stakeholder requirements, and managing expectations.
(68)A.integration B.scope C.process D.charter cnitpm参考答案:A
Cnitpm解析:

● Project (69) Management includes the processes required to ensure that the project includes all the work required, and only the work required, to complete the project successfully.
(69)A.Integration B.Scope C.Configuration D.Requirement cnitpm参考答案:B
Cnitpm解析:

● On some projects, especially ones of smaller scope, activity sequencing, activity resource estimating, activity duration estimating, and (70) are so tightly linked that they are viewed as a single process that can be performed by a person over a relatively short period of time.
(70)A.time estimating B.cost estimating
C.project planning D.schedule development cnitpm参考答案:D
Cnitpm解析:

● In approximating costs, the estimator considers the possible causes of variation of the cost estimates, including (71) 。
(71)A.budget B.plan C.risk D.contract cnitpm参考答案:C
Cnitpm解析:

● Project Quality Management must address the management of the project and the (72) of the project. While Project Quality Management applies to all projects, regardless of the nature of their product, product quality measures and techniques are specific to the particular type of product produced by the project.
(72)A.performance B.process C.product D.object cnitpm参考答案:C
Cnitpm解析:

● (73) is a category assigned to products or services having the same functional use but different technical characteristics. It is not same as quality.
(73)A.Problem B.Grade C.Risk D.Defect cnitpm参考答案:B
Cnitpm解析:

● Project (74) Management is the Knowledge Area that employs the processes required to ensure timely and appropriate generation, collection, distribution, storage, retrieval, and ultimate disposition of project information.
(74)A.Integration B.Time C.Planning D.Communication cnitpm参考答案:D
Cnitpm解析:

● The (75) process analyzes the effect of risk events and assigns a numerical rating to those risks.
(75)A.Risk Identification B.Quantitative Risk Analysis
C.Qualitative Risk Analysis D.Risk Monitoring and Control
cnitpm参考答案:B
Cnitpm解析: 

[1]   [2]   [3]   [4]   [5]   [6]   [7]   [8]   [9]   [10]   

温馨提示:因考试政策、内容不断变化与调整,信管网提供的以上信息仅供参考,如有异议,请考生以权威部门公布的内容为准!

分享至:
请使用浏览器的分享功能,把好文章分享给更多的人

信管网 - 信息系统项目管理专业网站

下载APP-在线学习

培训课程

0元畅享

考试题库

免费资料

APP下载