● Define Activities is the process of identifying the specific actions to be performed to produce the (71).
(71)A. project elements   B. work drafts
C. work package  D. project deliverables
Cnitpm 参考答案:D

● Project work packages are typically decomposed into smaller componentscalled activities to provide a basis for (72), scheduling, executing, and monitoring and controlling the project work.
(72)A. reviewing  B. estimating  C. auditing  D. expecting
Cnitpm 参考答案:B

● The Estimate Activity Resource process is closely coordinated with the (73)process.
(73)A. Estimate Costs   B. Sequence Activities
C. Plan Communications  D. Conduct Procurements
Cnitpm 参考答案:A

● Estimating activity durations uses information on activity scope of (74), required resource types, estimated resource quantities, and resource calendars.
(74)A. milestone  B. baseline  C. quality  D. work
Cnitpm 参考答案:D


●Developing the project schedule is often an iterative process. It determines the planned start and finish dates for project activities and milestones. Schedule development can require the review and revision of duration estimates and resource estimates to create an approved project schedule that can serve as a baseline to (75) progress.
(75)A. analyze  B. track   C. level  D. extend
Cnitpm 参考答案:B

2008年上半年
● The (71) is a general description of the architecture of a workflow management system used by the WFMC, in which the main components and the associated interfaces are summarized. The workflow enactment service is the heart of a workflow system which consists of several (72).
(71)A. waterfall model B. workflow reference model
C. evolutionary model D. spiral model
(72)A. workflow engines B. processes
C. workflow threads D. tasks Cnitpm参考答案:B、A
Cnitpm解析:

● The project maintains a current and approved set of requirements over the life of the project by doing the following:
• (73) all changes to the requirements
• Maintaining the relationships among the requirements, the project plans, and the work products
• ……
(73)A. Monitoring B. Managing C. Gathering D. Reducing Cnitpm参考答案:B
Cnitpm解析:

● The receiving activities conduct analyses of the requirements with the requirements provider to ensure that a compatible, shared understandin is reached on the meaning of the requirements. The result of this analysis and dialog is an (74) set of requirements.
(74)A. agreed-to B. agree-to
C. agree-to-do D. agree-with
Cnitpm参考答案:A
Cnitpm解析:

● During the project, requirements change for a variety of reasons. As needs change and as work proceeds, additional requirements are derived and changes may have to be made to the existing requirements. It is essential to manage these additions and changes efficiently and effectively. To effectively analyze the impact of the changes, it is necessary that the source of each requirement is known and the rationale for any change is documented. The project manager may, however, want to track appropriate measures of requirements volatility to judge whether new or revised (75)are necessary.
(75)A. proceedings B. controls
C. forecasting’s D. prelibations
Cnitpm参考答案:B 

[1]   [2]   [3]   [4]   [5]   [6]   [7]   [8]   [9]   [10]   

温馨提示:因考试政策、内容不断变化与调整,信管网提供的以上信息仅供参考,如有异议,请考生以权威部门公布的内容为准!

分享至:
请使用浏览器的分享功能,把好文章分享给更多的人

信管网 - 信息系统项目管理专业网站

下载APP-在线学习

培训课程

0元畅享

考试题库

免费资料

APP下载