During project execution, a key stakeholder expresses concern about the significant cost of a risk avoidance strategy being implemented by the project manager. What should the project manager tell the stakeholder? 在项目执行过程中,一位关键相关方对项目经理实施一项风险规避策略的大量成本表示担心,项目经理应该告诉相关方什么信息? ◑A.If the risk is realized, the cost of the project could be higher than the cost the risk avoidance strategy.如果这个风险变为现实,则项目成本可能高于风险规避策略的成本 ◑B.There is a high probability that the risk will be realized and, therefore, the risk avoidance counts are necessary.这个风险变成现实的概率很高,因此风险规避成本是必要的 ◑C.The risk has a high priority and impact on the risk register这个风险在风险登记册中的优先级和影响均较高 ◑D.They will terminate the risk avoidance strategy to reduce project expense他们将终止风险规避策略,以减少项目开支