信管网试题内容

试卷名称:课堂模拟二

考试年份:2021年上半年

试题来源:《课堂模拟二》在线考试

试题内容

The project manager received a call from the supplier saying that due to the flooding at the factory, deliverables will be seriously delayed. What should the project manager do next?
项目经理接到来自供应商的电话,说由于工厂发生洪水,可交付成果将发生严重延期,项目经理下一步应该怎么做?
◑A.Check the agreement or purchase order检查协议或采购订单
◑B.Update the project schedule更新项目进度计划
◑C.Submit a contract change request提交一份合同变更请求
◑D.Confirm the Statement of Work (SOW)确认工作说明书(SOW)

参考答案:A(仅供参考)

【解析】

普通会员无法查看试题解析。[开通试题解析服务]