A project manager is working on a project related to IT system development. A team member responsible for installing a server asks the project manager if it is acceptable to order a server with a faster processor than planned. The server is from the same manufacturer and costs approximately the same. Subject matter experts (SMEs) analyzed and determined corrective actions and change management procedures were followed.What should the project manager do next? 项目经理正在开展与IT系统开发相关的项目。负责安装服务器的一位团队成员询问项目经理是否可以订购具有比原计划更快处理器的服务器。这款服务器来自同一制造商,成本大致相同。主题专家(SME)分析并确定已遵循纠正措施和变更管理程序。项目经理下一步应该怎么做? ◑A.Update the issue log, change request, and work performance data.更新问题日志,变更请求和工作绩效数据 ◑B.Approve the change request, update the project management plan, and assess the enterprise environmental factors.批准变更请求,更新项目管理计划并评估事业环境因素 ◑C.Update the project documents, project management plan, and work performance reports.更新项目文件、项目管理计划和工作绩效报告 ◑D.Communicate with the stakeholders, update the change log, and execute the change.与相关方沟通、更新变更日志并执行变更