During the project execution phase, there was a conflict between team members due to lack of commitment, indifference to results and responsibilities. The cost performance index (CPI) began to decline. What should the project manager do? 在项目执行阶段,由于缺乏承诺、对结果和责任漠不关心,团队成员之间发生冲突。成本绩效指数(CPI)开始下降。项目经理应该怎么做? ◑A.Encourage constructive discussions, have meetings with the team, resolve the rationality of the project objectives, and conduct team performance assessments on a regular basis.鼓励建设性讨论,与团队开会,解决项目目标的合理性,并定期开展团队绩效评估。 ◑B.Report this to the Steering Committee.将这种情况上报给指导委员会 ◑C.Encourage constructive discussions, add the conflict to the issue log, and document corrective actions.鼓励建设性讨论,在问题日志中添加该冲突,并记录纠正措施 ◑D.Discuss the issue with executives and colleagues and update lessons learned.与管理层和同事讨论该问题,并更新经验教训。