A new functionality is approved for a software development project. Three weeks after approval a team member realizes that the development of this new functionality is already over budget.What should the project manager do next? 一项新功能被批准用于软件开发项目。在该功能获得批准三周后,一位团队成员得知这项新功能的开发已经超出预算。项目经理下一步应该怎么做? ◑A.Accept the budget overrun because it is already approved.接受预算超支,因为该功能已获得批准 ◑B.Stop the development of the new functionality.停止开发新功能 ◑C.Submit a change request.提交变更请求 ◑D.Update the cost baseline.更新成本基准