Midway through a project, a key project team member requests two months leave for personal matters. What should the project manager do first? 在一个项目中,一位关键项目团队成员因私事请假两个月,项目经理首先应该怎么做? ◑A.Ask this key team member if the leave can be postponed询问这位关键团队成员是否可以推迟请假 ◑B.Negotiate with the functional manager for a replacement与职能经理协商替换一名团队成员 ◑C.Evaluate the impact on the project评估对项目的影响 ◑D.Review the resource management plan审查志愿管理计划