A project is near completion and a team member report to project manager that there is an issue which will impact an important deadline. The weekly status report will be sent tomorrow to the major stakeholders. What should the project manager do next step?
A、Update the issue log, inform the sponsor, and use escalation process to report a possible delay to the stakeholders.
B、Inform the stakeholder in the weekly status report, discuss possible solutions with the stakeholders and request budget and schedule extensions.
C、Verify if this issue is in the risk plan, if it is not, include it and develop a mitigation plan.
D、Update the issue log, involve all the people that can help to solve the issue, and communicate the issue to the stakeholders.
温馨提示:因考试政策、内容不断变化与调整,信管网提供的以上信息仅供参考,如有异议,请考生以权威部门公布的内容为准!
相关推荐