( )is the process of identifying and documenting the specific actions to beperformed toproduce the project deliverable.
A.Plan schedule management
B.Develop Schedule
C.Sequence Activities
D.Define Activities
参考答案:D(仅供参考) 收藏

【解析】

普通会员无法查看试题解析。[开通试题解析服务]