信管网试题内容
信管网 导航

试题内容

The() phase is where the team members meet and learn about the project and their formal roles and responsibilities.
A.norming
B.storming
C.forming
D.performing
参考答案:C(仅供参考) 收藏

【解析】

普通会员无法查看试题解析。[开通试题解析服务]