Monitor Risk is not the process of () throughout the project.
A.monitoring the implementation of agree-upon risk response plans
B.Prioritizing individual project risks
C.Tracking and identifying new risks
D.Evaluating risk effectiveness
参考答案:B(仅供参考) 收藏