信管网试题内容
信管网 导航

试题内容

This ()is the work defined at the lowest level of the WBS for which cost and duration can be estimated and managed.
A.activity
B.planning package
C.work package
D.requirement
参考答案:C(仅供参考) 收藏

【解析】

普通会员无法查看试题解析。[开通试题解析服务]