A grid for mpping the probability of occurrence of each impact on project objectives if that risk occurs is used in ().
A.risk plan process
B.risk control process
C.risk response process
D.risk analysis process
参考答案:D(仅供参考) 收藏

【解析】

普通会员无法查看试题解析。[开通试题解析服务]