信管网试题内容

试卷名称:课堂模拟二

考试年份:2021年上半年

试题来源:《课堂模拟二》在线考试

试题内容

A project is working hard on deliverables to meet the planned schedule. One team member identifies that scope creep is affecting project costs. What should the project management do?
项目团队正在努力进行可交付成果的工作,以满足计划的进度。一名团队成员发现范围蔓延正在影响项目成本。项目经理应该怎么做?
◑A. Perform risk assessment and scope change management procedures执行风险评估和范围变更管理程序
◑B.Allow the scope creep and communicate it to the change control board (CCB) for approval允许范围蔓延,并与变更控制委员会(CCB)沟通以获得批准
◑C.Estimate the impact on the project and communicate the findings to project stakeholders估算对项目的影响,并将结果传达给项目相关方
◑D.Investigate why scope creep occurred and immediately initiate change management调查为什么会发生范围蔓延,并立即启动变更管理程序

参考答案:D(仅供参考)

【解析】

普通会员无法查看试题解析。[开通试题解析服务]