While developing the resource management plan, a project manager learns that the skill needed to complete a critical task is in short supply and high demand. The project manager notes this in the resource management plan.What other document should be updated to include this issue? 在制定资源管理计划时,一位项目经理得知,完成一项关键任务所需的技能组合供不应求且需求很高。项目经理将这个问题记录在资源管理计划中。若要包含这个问题,应该更新哪一份其他文件? ◑A.Procurement management plan 采购管理计划 ◑B.Risk management plan 风险管理计划 ◑C.Training manual 培训手册 ◑D.Team development process 团队开发过程