信管网试题内容

试卷名称:课堂模拟二

考试年份:2021年上半年

试题来源:《课堂模拟二》在线考试

试题内容

While identifying risks on a new project, the project team considers the following:·An unusual natural disaster might hit the building and cause it to fall.·The primary existing database storing all the project’s technical data is outdated and might fail.What should the project manager do?
在识别一个新项目的风险时,项目团队考虑到以下内容:·一次罕见的自然灾害可能会撞击建筑物并导致建筑物倒塌。·存储所有项目技术数据的主要现有数据库已过时,并可能会失效。项目经理应该怎么做?
◑A.Request the project to be transferred to a team in another geographical area请求将项目转移给另一个地理区域的团队
◑B.Advice the project to be canceled.建议取消该项目
◑C.Add the risks to the risk register将该风险添加进风险登记册
◑D.Inform the sponsor that the probability and impact are very low for both risks.通知发起人这两种风险的概率和影响都非常低

参考答案:C(仅供参考)

【解析】

普通会员无法查看试题解析。[开通试题解析服务]