A team member discovers that a new regulation may impact the hand-off date for a project at a remote site. What should the project manager do next? 一位团队成员发现一项新法规可能影响一个异地项目的交付日期,项目经理下一步应该怎么做? ◑A.Ask the project sponsor to accept the risk.要求项目发起人接收该风险 ◑B.Add extra time to the schedule.在进度计划中添加额外时间 ◑C.Update the risk register for risk analysis.更新风险登记册进行风险分析 ◑D.Ask the lead stakeholder to bring the change control board.请主要相关方将该问题提交给变更控制委员会(CCB)