信管网试题内容

试卷名称:课堂模拟二

考试年份:2021年上半年

试题来源:《课堂模拟二》在线考试

试题内容

After receiving the project charter from the sponsor, the project manager observes that a well-known, high-level risk has not been included. What should the project manager do?
项目经理在收到项目发起人的项目章程后,发现一个众所周知的高层级风险未列入其中。项目经理应该怎么做?
◑A.Include the risk in the statement of work (SOW)将该风险包含进工作说明书(SOW)中
◑B.Begin the Perform Integrated Change Control process开始实施整体变更控制过程
◑C.Discuss this with the project sponsor与项目发起人讨论该问题
◑D.Review the risk management plan to incorporate the risk修订风险管理计划,以包含该风险

参考答案:C(仅供参考)

【解析】

普通会员无法查看试题解析。[开通试题解析服务]