Project Integration Management includes the processes and activities to identify, define, combine, unify, and coordinate the various processes and project management activities within the Project Management Process Groups. (   ) process does not belong to Project Integration Management.
A. Developing project charter
B. Developing project management plan
C. Analyzing project risks
D.Monitoring and controlling project
参考答案:C(仅供参考) 收藏