信管网试题内容
信管网 导航

试题内容

The project budget has been finalized.Additional work has been discovered that was not planned for in the budget or project scope. ( )could provide the fund to cover the  newly discovered work item.
A. Contingency reserve
B. Project profit
C. Management reserve
D. Special fund

参考答案:C(仅供参考) 收藏

【解析】

普通会员无法查看试题解析。[开通试题解析服务]