信管网试题内容
信管网 导航

试题内容

A project manager believes that modifying the scope of the project may provide added value service for the customer. The project manager should(  ).
A.assign  change  tasks to project  members
B.call  a meeting of the  configuration  control  board
C.change  the  scope  baseline
D.postpone the modification until a separate enhancement project is funded after  this project  is completed according to the  original  baseline

参考答案:D(仅供参考) 收藏

【解析】

普通会员无法查看试题解析。[开通试题解析服务]