Which of he following Project Scope Management peocesses involves subdividing the major project deliverables into smaller, more manageablecomponents(  ).
A.Scope Planing
B.Scope Verification
C.Scope Change Control
D.Scope Definition

参考答案:D(仅供参考) 收藏