信管网试题内容

导航

试卷名称:2011年下半年系统集成项目管理工程师真题(上午)

考试年份:2011年下半年

试题来源:《2011年下半年系统集成项目管理工程师真题(上午)》在线考试

试题内容

A project manager is called to an informal meeting with the customer and a problem is raised. This problem has major implications for the project manager’s company, but the customer wants to pursue a solutionat the meeting, The project manager should(  ).
A.Tell the customer that he will not address any problems
B.Tell the customer that the problem is not sufficiently defined to company to a solution
C.Collect as much information on the problem without committing hiscompany to a solution
D.Give the customer a range of solutions that might be acceptable to his company

参考答案:C(仅供参考) 收藏

【解析】

普通会员无法查看试题解析。[开通试题解析服务]