信管网试题库

导航

系统集成项目管理工程师考试英语练习题十四

2020年07月06日来源:信管网 作者:cnitpm

1、 The project schedule is more than a document that lays out the activities over time to representthe time dimension of the project, it is a management tool to be used for decision making. As such , the schedule is used bythe roject management team to(  ).

A.Measure, delay, record, distribute , analyze, and direct

B.Plan, schedule, monitor, control, report, and forecast

C.Promote, highlight, monitor, control, forecast, and report

D.Emphasize, visualize, analyze, conceptualize, report and record

信管网参考答案:B

项目进度表是项目管理的一种时间维度,比时间安排更为重要。因此,项目管理团队使用该进度计划来()。

A、 测量、延迟、记录、分发、分析和指导

B、 计划、计划、监控、控制、报告和预测

C、 推广、突出、监控、控制、预测和报告

D、 强调、形象化、分析、概念化、报告和记录

查看解析:http://www.cnitpm.com/st/1018.html

2、 Which of he following Project Scope Management peocesses involves subdividing the major project deliverables into smaller, more manageablecomponents(  ).

A.Scope Planing

B.Scope Verification

C.Scope Change Control

D.Scope Definition

信管网参考答案:D

以下哪个项目范围管理流程涉及将主要项目交付物细分为更小、更易管理的组件()。

A、 范围规划

B、 范围验证

C、 范围变更控制

D、 范围定义

查看解析:http://www.cnitpm.com/st/1019.html

温馨提示:因考试政策、内容不断变化与调整,信管网提供的以上信息仅供参考,如有异议,请考生以权威部门公布的内容为准!

分享至:
请使用浏览器的分享功能,把好文章分享给更多的人

信管网 - 信息系统项目管理专业网站

下载APP-在线学习

培训课程

0元畅享

考试题库

免费资料

APP下载