1、 Plan Quality is the process of identifying quality requirements and standards for the project and product, and documenting how the project will demonstrate compliance.(  )is a method that analyze all the costs incurred over the life of the product by investment in preventing nonconformance to requirements, appraising the product or service for conformance to requirement, and failing to meet requirements.

A.Cost-Benefit analysis

B.Control charts

C.Quality function deployment

D.Cost of quality analysis

信管网参考答案:D

计划质量是确定项目和产品的质量要求和标准,并记录项目如何证明符合性的过程。()是一种分析产品寿命期内因投资防止不符合要求而产生的所有成本的方法,评价产品或服务是否符合要求,不符合要求。

A、 成本效益分析

B、 控制图

C、 质量功能配置

D、 质量成本分析

查看解析:http://www.cnitpm.com/st/1168.html

2、Project(  )is an uncertain event or condition that, if it occurs, hasa positive or a negative effect on at least one project objective, such as time,cost, scope, or  quality.

A.risk

B.problem

C.result

D.data

信管网参考答案:A

项目()是一个不确定的事件或条件,如果它发生,对至少一个项目目标(如时间、成本、范围或质量)产生正面或负面影响。

A、 风险

B、 问题

C、 结果

D、 数据

查看解析:http://www.cnitpm.com/st/1239.html

温馨提示:因考试政策、内容不断变化与调整,信管网提供的以上信息仅供参考,如有异议,请考生以权威部门公布的内容为准!