信息系统项目管理师考试英语练习题(十二)

2020年05月14日来源:信管网 作者:cnitpm

1、Developing the project schedule is often an iterative process. It determines the planned start and finish dates for project activities and milestones. Schedule development can require the review and revision of duration estimates and resource estimates to create an approved project schedule that can serve as a baseline to ( ) progress.

A. analyze    

B. track      

C. level     

D. extend

信管网解析:

开发项目进度表通常是一个迭代过程。它确定项目活动和里程碑的计划开始和结束日期。进度计划的制定可能需要对工期估算和资源估算进行审查和修订,以创建一个批准的项目进度计划,作为()进度的基线。

A、 分析

B、 轨道

C、 水平

D、 扩展

信管网参考答案:B

2、The ( ) is a  general description of the architecture of a workflow management system  used by  the WFMC, in which  the main components and  the associated interfaces are summarized. The workflow enactment service is the heart of a workflow system which consists of several .()  

(1)

A. waterfall model                      

B. workflow reference model            

C. evolutionary model                    

D. spiral model  

(2)

A. workflow engines                      

B. processes  

C. workflow threads                      

D. tasks  

信管网解析:

()是WFMC使用的工作流管理系统架构的一般描述,其中总结了主要组件和相关接口。工作流执行服务是由多个工作流系统组成的工作流系统的核心

(一)

A、 瀑布模型

B、 工作流参考模型

C、 进化模型

D、 螺旋模型

(二)

A、 工作流引擎

B、 过程

C、 工作流线程

D、 任务

信管网参考答案:B、A