试题1: 在ISO OSI/RM 中,( )实现数据压缩功能。
A. 应用层
B. 表示层
C. 会话层
D. 网络层
During the project, requirements change for a variety of reasons. As needs change and as work proceeds, additional requirements are derived and changes may have to be made to the existing requirements. It is essential to manage these additions and changes efficiently and effectively. To effectively analyze the impact of the changes, it is necessary that the source of each requirement is known and the rationale for any change is documented. The project manager may, however, want to track appropriate measures of requirements volatility to judge whether new or revised ( )are necessary.
A. proceedings
B. controls
C. forecasting’s
D. prelibations
在进行( )时可以采用期望货币值技术。
A. 定量风险分析
B. 风险紧急度评估
C. 定性风险分析
D. SWOT分析
用于项目范围确认的是( )。
A.项目范围说明书
B.工作包
C.范围基准
D. WBS
项目经理有责任处理项目过程中发生的冲突,以下解决方法中,()会使冲突的双方最满意,也是冲突管理最有效的一种方法。
A、双方沟通,积极分析,选择合适的方案来解决问题
B、双方各作出一些让步,寻求一种折中的方案来解决问题
C、将眼前的问题搁置,等待合适的时机再进行处理
D、冲突的双方各提出自己的方案,最终听从项目经理的决策
自由浮动时间和总浮动时间的区别是什么?
A、自由浮动时间不是影响完工日期的总浮动时间,而总浮动时间是自由浮动时间的累计总和
B、没有区别,两词在功能上相同,只是应用于不同领域
C、自由浮动时间是在不延误其紧后进度活动最早开始日期的前提下,某进度活动可以推迟的时间量;总浮动时间是在不延误项目完成日期或不违反进度制约因素的前提下,某进度活动可以推迟的总时间量
D、在不违反进度制约因素的前提下,进度活动的自由浮动时间等于关键路径的总浮动时间减去该活动的总浮动时间