71Big data can be described by four characteristics: Volume,Variety, locity and Veracity.()refers to the quantity of generated and stored date.  

AVolume

BVariety

CVelocity

DVeracity

信管网参考答案:A

最终答案以信管网题库为准:www.cnitpm.com

 

72is the extension of internet connectivity into physical devices and everyday objects.Embedded with electronics,internet connectivity and other forms of hardware (such as sensors), these devices can communicate and interact with others over the Internet ,and they can be remotely monitored and controlled.

ACloud Computing

BInternet of things

CBlock Chain

DArtificial Intelligence

信管网参考答案:B

最终答案以信管网题库为准:www.cnitpm.com

 

73is a process of developing a document that formally authorizes the existence of a project and provides the project manager with the authority to apply organizational resources to project activities.

ADevelop Project Charter

BManage Project Knowledge

CMonitor and Control Project work

DClose project

信管网参考答案:A

最终答案以信管网题库为准:www.cnitpm.com

 

 

74()is a process of developing a detailed description of the project and product

Acollect requirements

BDefinition scope

Cvalidate scope

DControl range

信管网参考答案:B

最终答案以信管网题库为准:www.cnitpm.com

 

75、()is a process of monitoring the status of the project to update the project costs and manage changes ti the cost baseline.

APlan Cost Management

BEstimate Costs

CDetermine Budget

DControl costs

信管网参考答案:D

最终答案以信管网题库为准:www.cnitpm.com

 