信管网试题分类练习

导航

英语试题:thefollowingaretheprojecttasks:taska(dur

2018年02月28日

试题来源:信管网 作者:cnitpm

试题分类:英语

The following are the project tasks:
Task A (duration 4 days)
Task B (duration 3 days)
Task C (duration 4 days)
Task D (duration 2 days)
Task E (duration 3 days)
Task F (duration 4 days)
Task D and task F can not start until task C is completed.  Task A and task B can start at any time after task C starts, but must complete before the end of the project.  Task E can only starts after task D is completed.  During the execution of task B, which starts 1 day later after task C starts, exception happened which will cause a 2-day delay for task B、 What action should be taken to ensure the project can be completed on time?
A、Add more resources to task B
B、 No action is necessary
C、 Reassign resources to tasks on
D、 Add more resources to task D

试题出处:http://www.ruantiku.com/shiti/3379610500.html
在下面提交答题后即可查看答案与考友试题分析

温馨提示:因考试政策、内容不断变化与调整,信管网提供的以上信息仅供参考,如有异议,请考生以权威部门公布的内容为准!

分享至:
请使用浏览器的分享功能,把好文章分享给更多的人

信管网 - 信息系统项目管理专业网站

下载APP-在线学习

培训课程

0元畅享

考试题库

免费资料

APP下载