系统集成项目管理工程师每日一练试题内容(2025/4/8)
试题1
建设方和承建方甲就某信息系统建设项目进行了多次合同谈判均未达成一致,未能签订系统建设合同,但在谈判期间建设方获悉了甲的行业关键技术指标。之后建设方与另一承建方乙经过合同谈判后就系统建设签订了合同,同时将甲的关键技术指标透露给乙,导致甲蒙受损失。下列说法中,( )是正确的。
A.建设方对甲蒙受的损失应承担赔偿责任
B.建设方和甲未签订合同,对甲蒙受的损失不应承担赔偿责任
C.乙和甲未签订合同,对甲蒙受的损失不应承担赔偿责任
D.甲的损失是由于其自身保密工作未做好,其损失应全部由其自身承担
查看答案
试题参考答案:A
试题2
The earned value technique is a commonly used method of performance measurement. It integrates project scope, cost, and schedule measures to help the project management team assess project performance. If a project ’ s Schedule Performance Index(SPI=EV/PV) value less than 1.0, it means that ( ).
A.the project is ahead of its planned schedule
B.less work was completed than was planned
C.the cost overrun for work completed
D.the cost under-run of performance to date
查看答案
试题参考答案:B
试题3
For any information system to serve its purpose, the information must be( )when it is needeD查看答案
试题参考答案:B
试题4
在()时。可以不进行招标。查看答案
试题参考答案:A
试题5
( ) is the process of identifying individual project risks as well as source of overall project risk, and documenting their characteristics,查看答案
试题参考答案:A
试题6
( ) is the sum of all budgets established for the work to be performed.查看答案
试题参考答案:B
试题7
() is the Process of defining how to conduct risk management Activities for a Project.查看答案
试题参考答案:C
试题8
( )is the process of identifying and documenting the specific actions to beperformed toproduce the project deliverable.查看答案
试题参考答案:D
试题9
Cloud computing is a style of computing in which dynamically scalabled often ( ) resources are provided as a service over the internet
A、 real
B、 rixed
C、 actual
D、 virtualized
查看答案
试题参考答案:D
试题10
( )属于《合同法》规定的合同内容。
A.风险责任的承担
B.争议解决方法
C.验收标准
D.测试流程
查看答案
试题参考答案:B