系统集成项目管理工程师每日一练试题内容(2025/2/15)
试题1
()不是国际标准化组织。查看答案
试题参考答案:B
试题2
Project manager process Group should divide into initiating Process Group.PlanningProcess Group and Controlling Process Group and Closing Process Group.查看答案
试题参考答案:C
试题3
In project management and systems engineering, ( ) is a deliverable-oriented breakdown of a project into smaller components. It is a key project deliverable that organizes the team's work into manageable sections.查看答案
试题参考答案:D
试题4
关于信息系统的有效性和可靠性,不正确的是()查看答案
试题参考答案:C
试题5
( )is the approved version of the time-phased project budget,excluding any management reserves,which can only be changed through formal change control precedures and is used as a basis for comparison to actual results.
A、The control accounts
B、Funding requirement
C、The cost estimates
D、The cost baseline
查看答案
试题参考答案:D
试题6
Project Integration Management includes the processes and activities to identify, define, combine, unify, and coordinate the various processes and project management activities within the Project Management Process Groups. ( ) process does not belong to Project Integration Management.查看答案
试题参考答案:C
试题7
以下关于信息的质量属性的叙述中,不正确的是()查看答案
试题参考答案:B
试题8
关于开放系统互联参考模型(OSI)的描述,不正确的是()。查看答案
试题参考答案:C
试题9
() is the Process of defining how to conduct risk management Activities for a Project.查看答案
试题参考答案:C
试题10
物联网是随着智能化技术的发展而发展起来的新的技术应用形式,从架构上来讲一般分为感知层、网络层和应用层,其中RFID技术一般应用于(1)。从物联网应用的角度来看,(2)不属于物联网的应用领域。查看答案
试题参考答案:A、D