  • 试题1

    下图中,如果按时完成活动1、2 和3 概率都是60%,活动4 在第6 天开始的概率是( )。

    A.30%
    B.40%
    C.22%
    D.60%

    查看答案

    试题参考答案:C

    试题解析与讨论:www.cnitpm.com/exam/ExamDay.aspx?t1=2&day=2025/1/20

  • 试题2

    A project manager is called to an informal meeting with the customer and a problem is raised. This problem has major implications for the project manager’s company, but the customer wants to pursue a solutionat the meeting, The project manager should(  ).
    A.Tell the customer that he will not address any problems
    B.Tell the customer that the problem is not sufficiently defined to company to a solution
    C.Collect as much information on the problem without committing hiscompany to a solution
    D.Give the customer a range of solutions that might be acceptable to his company

    查看答案

    试题参考答案:C

    试题解析与讨论:www.cnitpm.com/exam/ExamDay.aspx?t1=2&day=2025/1/20

  • 试题3

    过去几年小李完成了大量网卡驱动模块的开发,最快6天完成,最慢36天完成,平均21天完成。如今小李开发一个新网卡驱动模块,在21天到26天内完成的概率是( )。
    A.68.3%
    B.34.1%
    C.58.2%
    D.28.1%

    查看答案

    试题参考答案:B

    试题解析与讨论:www.cnitpm.com/exam/ExamDay.aspx?t1=2&day=2025/1/20

  • 试题4

    ()是一致同意建立并由公认的机构批准的文体、具有可重复使用的规则、指南、活动或结果特征,目的是在特定的背景下达到最佳秩序。
    A、标准
    B、法律
    C、法规
    D、流程

    查看答案

    试题参考答案:A

    试题解析与讨论:www.cnitpm.com/exam/ExamDay.aspx?t1=2&day=2025/1/20

  • 试题5

    A project life cycle is a collection of generally sequential project(1 )whose name and number are determined by the control needs of the organization or organizations involved in the project.The life cycle provides the basic (2 )for managing the project, regardless of the specific work involved.
    (1)A. phases          B. processes         C. segments       D. pieces
    (2)A.plan            B. fraction           C. main           D. framework

    查看答案

    试题参考答案:A、D

    试题解析与讨论:www.cnitpm.com/exam/ExamDay.aspx?t1=2&day=2025/1/20

  • 试题6

    The IoT architecture can be divided into three layers.  (     ) is the key layer to realize the foundational capabilities which support the electronic devices interact with physical world.
    A. Sensing layer
    B. Network layer
    C. Application layer
    D. Operation layer

    查看答案

    试题参考答案:A

    试题解析与讨论:www.cnitpm.com/exam/ExamDay.aspx?t1=2&day=2025/1/20

  • 试题7

    签订信息系统工程项目合同时有需要注意事项。下列选项中()在合同签订时不要考虑。
    A.当事人的法律资格              
    B.验收标准
    C.项目管理计划                 
    D.技术支持服务

    查看答案

    试题参考答案:C

    试题解析与讨论:www.cnitpm.com/exam/ExamDay.aspx?t1=2&day=2025/1/20

  • 试题8

    ()是整个数据仓库系统的核心。
    A.前端工具
    B.联机分析处理器
    C.数据的存储与管理
    D.数据源

    查看答案

    试题参考答案:C

    试题解析与讨论:www.cnitpm.com/exam/ExamDay.aspx?t1=2&day=2025/1/20

  • 试题9

    用户无需购买软件,而是租用基于web的软件管理企业经营活动,这种模式属于()。
    A、基础设施即服务laas
    B、平台即服务Paas
    C、软件即服务SaaS
    D、数据即服务DaaS

    查看答案

    试题参考答案:C

    试题解析与讨论:www.cnitpm.com/exam/ExamDay.aspx?t1=2&day=2025/1/20

  • 试题10

    关于招标过程的描述,不正确的是:()
    A.投标保证金不得超过招标项目估算价的2%,有效期应当与投标有效期一致
    B.招标人可以自行决定是否编制标底,一个招标项目只能有一个标底
    C.技术复杂、有特殊要求或者受自然环境限制,可以邀请招标
    D.资格预审文件或者招标文件的发售期不得少于 7 日

    查看答案

    试题参考答案:D

    试题解析与讨论:www.cnitpm.com/exam/ExamDay.aspx?t1=2&day=2025/1/20