  • 试题1

    Which of the following statement related to PMO is not correct?  (  )
    A. The specific form, function, and structure of a PMO is dependent upon the needs of the organization that it supports.
    B. One of the key features of a PMO is managing shared resources across all projects administered by the PMO.
    C. The PMO focuses on the specified project objectives.
    D. The PMO optimizes the use of shared organizational resources across all projects.

  • 试题2

    大数据储存技术首先需要解决的是数据海量化和快速增长需求,其次处理格式多样化的数据,谷歌文件系统(GFS)和Hadoop的( )奠定了大数据存储技术的基础。
    A、分布式文件系统
    B、分布式数据库系统
    C、关系型数据库系统
    D、非结构化数据分析系统
  • 试题3

    (  )is aproject mangement technique for measuring project performance and process.it has the ability to combine measurements of the projiect management triangle; scope time and costs.
    A、Critica path method(CPM)
    B、Earned value mangagemengt(EVM)
    C、Net present value method(NPVM)
    D、Expert judgment method(EJM)

系统集成项目管理工程师每日练习题答案解析(2024/11/25)

  • 试题1

    参考答案C

    参考解析:

    下列各项中,哪一个有关PMO的说法是错误的?()
    A.PMO的具体形式、职能和结构取决于它支持的组织的需求   
    B.PMO的关键特征之一是在所有PMO管理的项目之间共享和协调资源
    C.PMO关注于特定的项目目标
    D.PMO对所管理的所有项目共享资源的使用进行优化

  • 试题2

    参考答案A

    参考解析:谷歌文件系统(GFS)和Hadoop的分布式文件系统HDFS奠定了大数据存储技术的基础。大数据存储技术第二个要解决的是处理格式多样化的数据,这要求大数据存储管理系统能够对各种非结构化数揖;进行高效管理,代表产品如:谷歌BigTable和HadoopHbase等非关系型数据库(NoSQL)。
    大数据关键技术:http://www.cnitpm.com/pm1/45779.html

  • 试题3

    参考答案B

    参考解析:()是项目管理技术测量项目绩效和过程,必须结合项目管理三角:范围,时间和成本。
    A、关键路径法(CPM)
    B、挣值管理(EVM)
    C、净现值法(NPVM)
    D、专家判断法(EJM)