  • 试题1

    The key benefit of(   )is that it provides guidance and direction on how the project costs will be managed throughout the project.
    A. Plan Cost Management
    B. Control Cost
    C. Estimate Cost
    D. Determine Budget

    查看答案

    试题参考答案:A

    试题解析与讨论:www.cnitpm.com/exam/ExamDay.aspx?t1=2&day=2024/8/28

  • 试题2

    ()服务的重点不在于直接的经济效益,而更注重构建和形成紧密的产业生态。
    A.SaaS
    B.LaaS
    C.PaaS
    D.laaS

    查看答案

    试题参考答案:C

    试题解析与讨论:www.cnitpm.com/exam/ExamDay.aspx?t1=2&day=2024/8/28

  • 试题3

    ( )is the process of identifying and documenting the specific actions to beperformed toproduce the project deliverable.
    A.Plan schedule management
    B.Develop Schedule
    C.Sequence Activities
    D.Define Activities

    查看答案

    试题参考答案:D

    试题解析与讨论:www.cnitpm.com/exam/ExamDay.aspx?t1=2&day=2024/8/28

  • 试题4

    智能制造能力要素包括:(    )
    A.人员、技术、生产、资金
    B.工艺、产品、销售、服务
    C.采购、计划、调度、生产
    D.人员、技术、资源、制造

    查看答案

    试题参考答案:D

    试题解析与讨论:www.cnitpm.com/exam/ExamDay.aspx?t1=2&day=2024/8/28

  • 试题5

    根据《中华人民共和国招投标法》中关于招投标程序的规定,( )是错误的。
    A、招标人如采用公开招标方式的,应当公开发布招标公告;依法必须进行招标的项目的招标公告,应当通过国家指定的报刊、信息网络或者其他媒介发
    B、招标人根据招标项目的具体情况,可以组织潜在投标人踏勘项目现场
    C、投标人应当在招标文件要求提交投标文件的截止时间前将投标文件送达投标地点。招标人收到投标文件后,应当签收,并当面开启进行初审。
    D、评标由招标人依法组建的评标委员会负责,中标结果确定后,评标委员会成员的名单可以在中标公告中公布

    查看答案

    试题参考答案:C

    试题解析与讨论:www.cnitpm.com/exam/ExamDay.aspx?t1=2&day=2024/8/28

  • 试题6

    (   )不是数字政府建设的关键词。
    A.共享
    B.互通
    C.便利
    D.交易

    查看答案

    试题参考答案:D

    试题解析与讨论:www.cnitpm.com/exam/ExamDay.aspx?t1=2&day=2024/8/28

  • 试题7

    ( ) is the process of identifying individual project risks as well as source of overall project risk, and documenting their characteristics.
    A. Identify Risks
    B. Monitor Risks
    C. Implement Risk Responses
    D. Plan Risk Management

    查看答案

    试题参考答案:A

    试题解析与讨论:www.cnitpm.com/exam/ExamDay.aspx?t1=2&day=2024/8/28

  • 试题8

    Project () includes making choices about resource allocation balancing competing demands examining any alternative approaches tailoring the processes to meet the project objectives and managing the inter dependencies among the Project Management
    Knowledge Areas.
    A.schedule management
    B.scope management
    C.integration management
    D.resource management

    查看答案

    试题参考答案:C

    试题解析与讨论:www.cnitpm.com/exam/ExamDay.aspx?t1=2&day=2024/8/28

  • 试题9

    系统分析阶段的工作成果体现在()中,这是系统建设的必备文件。它既是和用户确认需求的基础,也是下一个阶段的工作依据。
    A.需求说明书
    B.工作说明书
    C.采购说明书
    D.系统说明书

    查看答案

    试题参考答案:D

    试题解析与讨论:www.cnitpm.com/exam/ExamDay.aspx?t1=2&day=2024/8/28

  • 试题10

    ()标准规定了计算机软件生存周期内各类软件产晶的基本测试方法、过程和准则,适用于计算机软件生存周期全过程,适用于计算机软件的开发机构、测试机构及相关人员。
    A.GB/T 11457《信息技术软件工程术语》
    B.GB/T 25000《系统与软件工程系统与软件质量要求和评价(SQuaRE)》
    C.GB/T 15532《计算机软件测试规范》
    D.GB/Z 31102《软件工程软件工程知识体系指南》

    查看答案

    试题参考答案:C

    试题解析与讨论:www.cnitpm.com/exam/ExamDay.aspx?t1=2&day=2024/8/28

温馨提示:因考试政策、内容不断变化与调整,信管网提供的以上信息仅供参考,如有异议,请考生以权威部门公布的内容为准!

分享至:

信管网 - 信息系统项目管理专业网站

下载APP-在线学习