系统集成项目管理工程师每日一练试题内容(2024/3/21)

  • 试题1

    Perform Quality Control is the process of monitoring and recording results of executing the Quality Plan activities to assess performance and recommend necessary changes.(    ) are the techniques and tools in performing quality control.
    ①Statistical sampling            ②Run chart                ③Control charts
    ④Critical Path Method            ⑤Pareto chart           ⑥Cause and effect diagrams
    A.①②③④
    B.②③④⑤
    C.①②③⑤⑥
    D.①③④⑤⑥

    查看答案

    试题参考答案:C

    试题解析与讨论:www.cnitpm.com/st/1167402.html

  • 试题2

    The work that needs to be accomplished to deliver a product, service ,or result with the specified features and functions is called ( ).
    A、Scope management
    B、Integrated management
    C、SOW
    D、PMO

    查看答案

    试题参考答案:A

    试题解析与讨论:www.cnitpm.com/st/43671504.html

  • 试题3

    根据《信息技术 软件工程术语 GB/T11457-2006》。( )是评价系统或软件,以确定软件开发周期中的一个给定阶段的产品是否满足在阶段的开始确立的需求的过程。
    A、认证
    B、确认
    C、审计
    D、验证

    查看答案

    试题参考答案:D

    试题解析与讨论:www.cnitpm.com/st/2824973.html

  • 试题4

    ()is not included in the main contents of the operation and maintenance of the  information system.
    A.Daily operation and maintenance  
    B.System change
    C.Security management                                  
    D.Business change

    查看答案

    试题参考答案:D

    试题解析与讨论:www.cnitpm.com/st/2325420559.html

  • 试题5

    根据GB/T  12504-1990《计算机软件质量保证计划规范》规定,基本文档最小集可不包括(1)。(2)是在软件发布前,要对软件进行检查,以确认已满足在软件规格说明书中的规定的所有需求。
    (1)A、软件需求规格说明书
    B、软件验证与确认计划
    C、软件配置管理计划
    D、软件设计说明书
    (2)A、软件需求评审
    B、软件验证与确认评审
    C、功能检查
    D、物理检查

    查看答案

    试题参考答案:C、C

    试题解析与讨论:www.cnitpm.com/st/2843827590.html

  • 试题6

    The project manager can arrange the project schedule management activities in the following order()。
    ①Plan schedule Management    ②Define Activities
    ③Estimate Activity Durations     ④Sequence Activities
    ⑤Control Schedule    ⑥Develop Schedule
    A.①②③④⑤⑥
    B.②④③⑥⑤①
    C.①③④②⑥⑤
    D.①②④③⑥⑤

    查看答案

    试题参考答案:D

    试题解析与讨论:www.cnitpm.com/st/5689224625.html

  • 试题7

    () management  includes  negotiating  the  terms and conditions in contracts and ensuring compliance with. the terms and conditions, as well as documenting and agreeing on any changes or amendments  that may arise during its implementation or execution. 
    A.Contract
    B.Document
    C.Communication
    D.Risk

    查看答案

    试题参考答案:A

    试题解析与讨论:www.cnitpm.com/st/140888465.html

  • 试题8

    A schedule is  commonly used in project planning and project portfolio management. () on a schedule may be closely related to the work breakdown structure (WBS)terminal  elements, the  statement of  work, or a  contract  data requirements list.
    A.Essences
    B.Elements
    C.Purposes
    D.Issues

    查看答案

    试题参考答案:B

    试题解析与讨论:www.cnitpm.com/st/140874967.html

  • 试题9

    The ( ) refers to the integration of complex physical machinery with networked sensors and software. It draws together fields such as machine learning, big data, the Internet of things and machine-to-machine communication to ingest data form machines, analyze it (often in real-time), and use it to adjust operations.
    A. Industrial internet              
    B. factory internet
    C. Industrial web                 
    D. business internet

    查看答案

    试题参考答案:A

    试题解析与讨论:www.cnitpm.com/st/1940026760.html

  • 试题10

    合同法律关系是指由合同法律规范调整的在民事流转过程中形成的( )
    A.买卖关系
    B.监督关系
    C.权利义务关系
    D.管控关系

    查看答案

    试题参考答案:C

    试题解析与讨论:www.cnitpm.com/st/1352466.html

温馨提示:因考试政策、内容不断变化与调整,信管网提供的以上信息仅供参考,如有异议,请考生以权威部门公布的内容为准!