信管网每日一练
系统集成项目管理工程师 - 每日一练 导航

系统集成项目管理工程师每日一练试题(2024/2/2)

2024年02月03日来源:信管网 作者:cnitpm

系统集成项目管理工程师当天每日一练试题地址:www.cnitpm.com/exam/ExamDay.aspx?t1=2

往期系统集成项目管理工程师每日一练试题汇总:www.cnitpm.com/class/27/e2_1.html

系统集成项目管理工程师每日一练试题(2024/2/2)在线测试:www.cnitpm.com/exam/ExamDay.aspx?t1=2&day=2024/2/2

点击查看:更多系统集成项目管理工程师习题与指导

系统集成项目管理工程师每日一练试题内容(2024/2/2)

  • 试题1

    根据《计算机软件文档编制规范GB/T 8567-2006》,文档在形成后都要求进行质量控制,主要活动包括()
    ①评审    ②可行性测试    ③走查    ④审查
    A、①②③④  
    B、①②  
    C、①③④   
    D、②③④

    查看答案

    试题参考答案:B

    试题解析与讨论:www.cnitpm.com/st/121384179.html

  • 试题2

    ()is a process of developing a detailed description of the project and product
    A、collect requirements
    B、Definition scope
    C、validate scope
    D、Control range

    查看答案

    试题参考答案:B

    试题解析与讨论:www.cnitpm.com/st/410791250.html

  • 试题3

    ( ) is a subset of artificial intelligence in the field of computer science that often uses statistical techniques to give computers the abillity to “learn” (i.e., progressively improve performance on a specific task) with data. Without being explicitly programmed.
    A、Machine learning
    B、Program language learning
    C、Natural language learning
    D、Statistical learning

    查看答案

    试题参考答案:A

    试题解析与讨论:www.cnitpm.com/st/3951929500.html

  • 试题4

    某项目建设内容包括机房的升级改造、应用系统的开发以及系统的集成等。招标人于2010 年3 月25 日在某国家级报刊上发布了招标公告,并规定4 月20 日上午9 时为投标截止时间和开标时间。系统集成单位A、B、C 购买了招标文件。在4 月10 日,招标人发现已发售的招标文件中某技术指标存在问题,需要进行澄清,于是在4 月12 日以书面形式通知A、B、C 三家单位。根据《中华人民共和国招标投标法》,投标文件截止日期和开标日期应该不早于( )。
    A.5 月5 日
    B.4 月22 日
    C.4 月25 日
    D.4 月27 日

    查看答案

    试题参考答案:D

    试题解析与讨论:www.cnitpm.com/st/1229424.html

  • 试题5

     In project management, a ( )is a list of a project’s milestones, activities, and deliverables, usually with intended start and finish date. Those items are often estimated in terms of resource allocation, budget and duration, linked by dependencies and scheduled events.
    A. schedule                 
    B. WBS                           
    C. SOW                  
    D. charter

    查看答案

    试题参考答案:A

    试题解析与讨论:www.cnitpm.com/st/121504183.html

  • 试题6

    In project time management, activity definition is the process of identifying and documenting the specific action to be performed to produce the project deliverables. ()are not output of activity definition.
    A.Activity list
    B.Work Breakdown Structures
    C.Activity Attributes      
    D.Milestone Lists

    查看答案

    试题参考答案:B

    试题解析与讨论:www.cnitpm.com/st/2325527650.html

  • 试题7

    Project(  )is an uncertain event or condition that, if it occurs, hasa positive or a negative effect on at least one project objective, such as time,cost, scope, or  quality.
    A.risk
    B.problem
    C.result
    D.data

    查看答案

    试题参考答案:A

    试题解析与讨论:www.cnitpm.com/st/1239427.html

  • 试题8

    某信息系统集成项目采用挣值分析技术进行成本控制,假设当前状态数据如下表所示,则该项目的CPI、EAC、当前项目的状态分别是( )。

    A.0.8,12500元,进度滞后且成本超支
    B.0.8,12500元,进度提前且成本超支
    C.1.25,12500元,进度滞后且成本低于预算
    D.1.25,12500元,进度提前且成本低于预算

    查看答案

    试题参考答案:A

    试题解析与讨论:www.cnitpm.com/st/991342.html

  • 试题9

    在项目实施期间的某次周例会上,项目经理向大家通报了项目目前的进度。根据以下表格特,目前的进度()。

    A.提前计划7%
    B.落后计划15%
    C.落后计划7%
    D.提前计划15%

    查看答案

    试题参考答案:C

    试题解析与讨论:www.cnitpm.com/st/140826317.html

  • 试题10

    依据《“十四五”软件和信息技术服务业发展规划》,“加快突破”金融核心业务系统的建筑信息建模和建筑防火模拟智慧能源管理、智能交通管理、智能办公室等,属于()任务的工作内容。
    A.重点突破工业软件
    B.协同攻关应用软件
    C.聚力攻坚基础软件
    D.前瞻布局新型平台软件

    查看答案

    试题参考答案:B

    试题解析与讨论:www.cnitpm.com/st/519561399.html

温馨提示:因考试政策、内容不断变化与调整,信管网提供的以上信息仅供参考,如有异议,请考生以权威部门公布的内容为准!

分享至:

信管网 - 信息系统项目管理专业网站

下载APP-在线学习

培训课程

0元畅享

考试题库

免费资料

客服咨询