系统集成项目管理工程师每日一练试题内容(2023/9/12)

  • 试题1

    某项目的网络图如下,活动D的自由浮动时间为() 天

    A、0
    B、1
    C、2
    D、3

    查看答案

    试题参考答案:B

    试题解析与讨论:www.cnitpm.com/st/4136216008.html

  • 试题2

    ()是一致同意建立并由公认的机构批准的文体、具有可重复使用的规则、指南、活动或结果特征,目的是在特定的背景下达到最佳秩序。
    A、标准
    B、法律
    C、法规
    D、流程

    查看答案

    试题参考答案:A

    试题解析与讨论:www.cnitpm.com/st/4584921205.html

  • 试题3

    Managing risk and documenting them is very important in project planning process. You are in the process of defining key risks, including constraints and assumptions, and planned responses and contingencies. These details will be included in the( )
    A. project management plan
    B. project baseline
    C. risk response plan
    D. risk baseline

    查看答案

    试题参考答案:A

    试题解析与讨论:www.cnitpm.com/st/2879992.html

  • 试题4

    ()is the action to eliminate the caues or ruduce the likehood of recurrence of a detected Nonconformity or  other undersirabee  situatlon.
    A.corrective action
    B.continual improvement
    C.known error
    D.preventive action

    查看答案

    试题参考答案:A

    试题解析与讨论:www.cnitpm.com/st/5202118997.html

  • 试题5

    Software engineers apply the principles of software engineering to the design, development, ( ),testing, and evaluation of the software and systems that make computers or anything containing software work.
    A. Requirement
    B. construction
    C. service
    D. maintenance

    查看答案

    试题参考答案:D

    试题解析与讨论:www.cnitpm.com/st/194012063.html

  • 试题6

    In a project plan, when the project manager schedules activities, he (or she) often uses ( ) method,precedence relationships between acticities are represented by cireles connected by one or more arrows. The length of the arrow represents the duration of the relevant activity.
    A、causality diagram
    B、Gantt chart
    C、histogram
    D、arrow diagram

    查看答案

    试题参考答案:D

    试题解析与讨论:www.cnitpm.com/st/3952210979.html

  • 试题7

    A (    ) is a dedicated storage network that provides access to consolidated,block level storage.It is primarily used to mark storage devices accessible to servers so that the devices appear as locally attached to the operating system.
    A.network-attached storage
    B.storge area network
    C.direct attached storage
    D.computer cluster

    查看答案

    试题参考答案:B

    试题解析与讨论:www.cnitpm.com/st/941324.html

  • 试题8

    根据《中华人民共和国政府采购法》。关于询价采购的程序,下面说法不正确的是( )。
    A.询价小组应由采购人的代表和有关专家共五人以上的单数组成。其中专家的人数不得少于成员总数的三分之二
    B.询价小组按照采购需求,从符合相应资格条件的供应的商名单中确定不少于三家的供应商,并向其发出询价通知书让其报价
    C.询价小组应要求被询价的供应商一次报出不得更改的价格
    D.采购人员根据符合采购需求、质量和服务同等且报价最低的原则确定成交供应商,并将结果通知所有被询价的未成交的供应商

    查看答案

    试题参考答案:A

    试题解析与讨论:www.cnitpm.com/st/2825973.html

  • 试题9

    合同的内容就是当事人订立合同时的各项合同条款,下列不属于项目合同主要内容的是( )。
    A.项目费用及支付方式
    B.项目干系人管理
    C.违约责任
    D.当事人各自权力、义务

    查看答案

    试题参考答案:B

    试题解析与讨论:www.cnitpm.com/st/1293446.html

  • 试题10

    某项目计划安排为:2014年4月30日完成1000万元的投资任务。在当期进行项目绩效时评估结果为:完成计划投资额的90%,而CPI为50%,这时的项目实际花费为( )万元。
    A、450       
    B、900           
    C、1800         
    D、2000

    查看答案

    试题参考答案:C

    试题解析与讨论:www.cnitpm.com/st/12606926.html