71、Many Chinese museums and art galleries rolled out online exhibitions,courses and other online services,allowing netizens to take virtual tours and enjoy splendid art feasts online. Which one is not the technology support to this service()。
A.5G
B.Virtual rreality (VR)
C.Ultrahigh definition video
D.Block chain
信管网参考答案:D
查看解析:www.cnitpm.com/st/5382411100.html
72、()is not the application scenario of artificial intelligence.
A.autonomous robot
B.face recognition
C.self-driving
D.conditioned reflex
信管网参考答案:A
查看解析:www.cnitpm.com/st/5382518863.html
73、This ()is the work defined at the lowest level of the WBS for which cost and duration can be estimated and managed.
A.activity
B.planning package
C.work package
D.requirement
信管网参考答案:C
查看解析:www.cnitpm.com/st/5382611557.html
74、Monitor Risk is not the process of () throughout the project.
A.monitoring the implementation of agree-upon risk response plans
B.Prioritizing individual project risks
C.Tracking and identifying new risks
D.Evaluating risk effectiveness
信管网参考答案:B
查看解析:www.cnitpm.com/st/5382715257.html
75、The() phase is where the team members meet and learn about the project and their formal roles and responsibilities.
A.norming
B.storming
C.forming
D.performing
信管网参考答案:C
查看解析:www.cnitpm.com/st/5382816222.html