() is the process of developing options, selecting strategies, and agreeing on actions to address overall project risk exposure, as well as to treat individual project risks.
A. Plan risk responses
B. Plan risk management
C. Implement risk responses
D. Perform quantitative risk analysis
参考答案:A(仅供参考) 收藏

【解析】

普通会员无法查看试题解析。[开通试题解析服务]