Project selection methods involve measuring value or attractiveness to the project owner or sponsor and may include other organizational decision criteria. (  )is not a project selection method.
A.Benefit contribution
B.Expert judgment
C.Scoring models
D.Flow charting

参考答案:D(仅供参考) 收藏