信管网试题内容
信管网 导航

试题内容

A critical path for a project is the series of activities that determine ( ) by which the project can be completed.
A.the earliest time
B.the latest time
C.the total time
D.the free time

参考答案:C(仅供参考) 收藏

【解析】

普通会员无法查看试题解析。[开通试题解析服务]