Project Communications Management consists of two parts. The first part is developing a strategy to ensure communication is effective for stakeholders. The second part is carrying out the activities necessary to implement the( ).
A. communication tools
B. communication technology
C. communication cost
D. communication strategy
参考答案:D(仅供参考) 收藏