试卷名称:2005年上半年信息系统项目管理师真题(上午)

考试年份:2005年上半年

试题来源:《2005年上半年信息系统项目管理师真题(上午)》在线考试

试题内容

(1 ) is a method of constructing a project schedule network diagram that uses boxes or rectangles,referred to as nodes,to represent activites and connects them with arrows that asow the dependencies.This method includes following types of dependcies orprecedence relationships: (2 )the initiation of the successor activity, depends upon the completion of the predecessor activity.(3)the initiation of the successor activity, depends upon the initiation of the predecessor activity.
(1)A.PDM                B.CPM               C.PERT             D.AOA
(2)A.F-S                  B.F-F                C.S-F               D.S-S
(3)A.F-S                  B.F-F                C.S-F               D.S-S

参考答案:A、A、D(仅供参考) 收藏