 ()is the hierarchical breakdown of the entire scope of work by the project team to accomplish the project objectives and create the required deliverables,It provides detailed deliverable,activity,and scheduling information about each component in the work breakdown structure.
A.OLA
B.SLA
C.SOP
D.WBS
参考答案:D(仅供参考) 收藏