The IT service manager resigns from a project that meets the scheduleand budget. After hiring an alternativenew manager, the team is opposed to the comments from the new manager. The team is at ( ) developmentstages。
A.Forming
B.Storming
C.Norming
D.Performing
参考答案:A(仅供参考) 收藏

【解析】