Project () includes making choices about: resource allocation,balancing competing demands, examining any alternative approaches, tailoring the processes to meet the project objectives and managing the interdependencies among the Project Management Knowledge Areas.
A.schedule management
B.scope management
C.integration management
D.resource management
参考答案:C(仅供参考) 收藏