A project feasibility study determined what product should be created. Now, a change request has been approved to develop another product that contradicts the original requirements. Data analysis was conducted before the change request was approved. What should the project manager do? 项目可行性研究确定了应该创建什么产品。现在,开发与原始需求冲突的另一种产品的一项变更请求,已经获得批准,在变更请求获得批准前已进行数据分析。项目经理应该怎么做? ◑A.Implement the change request实施该变更请求 ◑B.Reject the change request拒绝该变更请求 ◑C.Request a detailed report of the data analysis请求详细的数据分析报告 ◑D.Request a feasibility study of the new product请求新产品的可行性研究