信管网试题内容

试卷名称:课堂模拟二

考试年份:2021年上半年

试题来源:《课堂模拟二》在线考试

试题内容

Based on project progress made to date, a project team wants to change the risk management approach they chose at the beginning of the project. The project manager approves this request to ensure project success, and project activities continue.What should the project manager have done instead?
根据迄今为止取得的项目进展,项目团队希望改变他们在项目开始时选择的风险管理方法。为了确保项目成功,项目活动继续进行,项目经理批准了这一请求。项目经理本应该怎么做?
◑A.Referred to the risk management plan, and encouraged the project team to follow the project’s agreed-upon change control process.查阅风险管理计划,并鼓励项目团队遵循项目的约定变更控制流程
◑B.Refuse to make the changes, as the approach was already agreed-upon by the stakeholders拒绝进行变更,因为这种方法已经获得相关方的同意
◑C.Told the project team that the risk management approach was determined based on the needs of the project and cannot be changed.告诉项目团队,风险管理方法是根据项目需求确定的,不能改变
◑D.Rewarded the project team for identifying a new risk management approach.因项目团队确定新的风险管理方法而奖励团队

参考答案:A(仅供参考)

【解析】

普通会员无法查看试题解析。[开通试题解析服务]