信管网试题内容

试卷名称:课堂模拟二

考试年份:2021年上半年

试题来源:《课堂模拟二》在线考试

试题内容

A project that should have been 80 percent complete by now is only 75 percent complete. The total project budget is US$100, 000 and the actual cost of work performed (ACWP) is US$72, 000.What can be determined from this information?
到目前为止本该完成百分之八十的一个项目只完成了百分之七十五,项目总预算为100,000美元,已完成工作实际成本(ACWP)为72,000美元。根据这些信息可以确定什么?
◑A.The project is under budget, has a schedule performance index (SPI) of 0.94, and a cost performance index (CPI) of 1.04.该项目低于预算,与进度绩效指数(SPI)为0.94,成本绩效指数(CPI)为1.04
◑B.The project is over budget, has an SPI of l.07, and a CPI of 0.96.该项目超出预算,其SPI为1.07,CPI为0.96
◑C. The project is over Budget, has an SPI of 0.96, and a CPI of 1.04.该项目超出预算,其SPI为0.96,CPI为1.04
◑D.The project is under budget, has an SPI OF 0.94, and a CPI of 0.96.该项目低于预算,其SPI为0.94,CPI为0.96

参考答案:A(仅供参考)

【解析】

普通会员无法查看试题解析。[开通试题解析服务]